Previous Year Papers

Download Solved Question Papers Free for Offline Practice and view Solutions Online.

Test Series

Take Zigya Full and Sectional Test Series. Time it out for real assessment and get your results instantly.

Test Yourself

Practice and master your preparation for a specific topic or chapter. Check you scores at the end of the test.
Advertisement

 Multiple Choice QuestionsMultiple Choice Questions

Advertisement
101.

A sum of money is sufficient to pay A's wages for 21 days and B's wages for 28 days. The same money is sufficient to pay the wages of both for

  • 24 1 half space days

  • 12 days

  • 12 1 fourth space days

  • 14 days

27 Views

102.

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time?

  • 40

  • 50

  • 48

  • 56

29 Views

103.

A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C, they can finish it in 5 days. If they are paid ₹ 960 for the whole work how much money A gets?

  • ₹ 480

  • ₹ 240

  • ₹ 320

  • ₹ 400

31 Views

104.

Ronald and Elan are working on an assignment. Ronald takes 6h to type 32 pages on a computer, While Elan takes 5 h to type 40 pages. How much time will they take, working together on two different computers to type an assignment of 110 pages?

  • 7 h 30 min

  • 8 h

  • 8 h 15 min

  • 8 h 25 min

40 Views

Advertisement
105.

One man,  3 women and 4 boys can do a piece of work in 96 h,  2 men and 8 boys can do it in 80 h, 2 men and 3 women can do it in 120 h. 5 men and 12 boys can do it in

  • 39 1 over 11 straight h

  • 42 7 over 11 straight h

  • 43 7 over 11 straight h

  • 44 h

35 Views

106.

A and B together can do a piece of work in 6 days. If A can alone do the work in 18 days, then the number of days required for B to finish the work is

  • 9

  • 10

  • 12

  • 15


107.

A, B and C can complete a work in 20, 24 and 30 days respectively. All three of them starts together but after 4 days A leaves the job and B left the job 6 days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?

  • 10 days

  • 12 days

  • 14 days

  • 16 days


108.

Asif is twice as good as workman as Bashir and together they finish a piece of work in 30 days. In how many days will Asif alone finish the work?

  • 90 days

  • 45 days

  • 60 days

  • 75 days


Advertisement
Advertisement