 Multiple Choice QuestionsMultiple Choice Questions

1.

A can complete a piece of work in 2 days, and B in 3 days. With the help of C they together completed it in one day. C alone could complete the work in

  • 4 days

  • 5 days

  • 6 days

  • 6 days

144 Views

2.

Amar can complete 1 fourth of a work in 3 days and Shankar can complete 1 over 6 of the same work in 4 days. How much will Amar get if both work together and are paid Rs. 1,800 in all?

  • Rs. 600

  • Rs. 1000

  • Rs. 1080

  • Rs. 1080

125 Views

Advertisement

3.

30 workers can complete a job in 36 days. After 30 days, some more workers joined and the job was completed 2 days earlier. How many new workers joined?

  • 13

  • 15

  • 17

  • 17


B.

15

Part of the work completed in 30 days
    1 over 36 cross times 30 space equals space 5 over 6
Now, 
therefore space space space space fraction numerator straight M subscript 1 straight D subscript 1 over denominator straight W subscript 1 end fraction space equals space fraction numerator straight M subscript 2 straight D subscript 2 over denominator straight W subscript 2 end fraction
rightwards double arrow space space space space fraction numerator 30 space cross times space 30 over denominator begin display style 5 over 6 end style end fraction space equals space fraction numerator straight M subscript 2 space cross times space 4 over denominator begin display style 1 over 6 end style end fraction
rightwards double arrow space space space space space straight M subscript 2 space equals space fraction numerator 30 space cross times space 30 over denominator 5 space cross times space 4 end fraction space equals space 45
∴   Number of new workers = 45 - 30 = 15

217 Views

Advertisement
4.

P takes 5 hours more than Q to complete a work. Working together they completed the work in 6 hours. Q alone could complete the work in

  • 8 hours

  • 10 hours

  • 12 hours

  • 12 hours

144 Views

Advertisement
5.

A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work together but A left 8 days before the completion of the work and B, 12 days before the completion of the work. Only C worked upto the end. In how many days was the work completed?

  • 24

  • 25

  • 27

  • 27

223 Views

6.

A and B can do a piece of work in 15 days. B and C can do a similar work in 12 days and C and A in 10 days. How many days will A take to do the work by himself?

  • 13

  • 24

  • 40

  • 40

134 Views

7.

A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after

  • 6 days

  • 9 days

  • 12 days

  • 12 days

109 Views

8.

2 men and 1 woman can complete a piece of work in 14 days while 4 women and 2 men can do the same work in 8 days. If a man gets Rs. 180 per day, then a woman will get per day

  • Rs. 150

  • Rs. 140

  • Rs. 120

  • Rs. 120

166 Views

Advertisement
9.

A carpenter can build a cupboard in 60 hours. After 15 hours he takes a break. What fraction of the cupboard is yet to be built?

  • 0.5

  • 0.9

  • 0.75

  • 0.25


10.

A works twice as fast as B. If B can complete a piece of work independently in 12 days, then what will be the number of days taken by A and B together to finish the work? 

  • 4

  • 6

  • 8

  • 18

704 Views